Phase 5: Safeguarding the Port for Future Generations

Phase 5 expansion will enable the Port to attract world leaders to the Firth for the benefit of the region – including those developing massive offshore wind projects off our coast.

Phase 5

What is Phase 5?

Since the Port was established in the 1970s, the world has changed. The renewables industry has boomed – with technology rapidly growing in size; the size of rigs has increased; and cruise ships are larger than ever.

To prepare for the future, safeguard jobs and create more business opportunities, more space and modern facilities are needed to accommodate the vessels that would like to visit and bring their projects or passengers here.

  • The depth of the Cromarty Firth’s water means it can accommodate the largest vessels, which many other ports cannot.
  • The Port welcomes more cruise passengers than any other port in Scotland.

The Port is one of only two in the UK set to benefit from the UK Government’s Floating Offshore Wind Manufacturing Investment Scheme (FLOWMIS) for this expansion, and has been selected as one of three Scottish projects chosen to progress in the SOWEC Strategic Investment Model (SIM).

Public Notice

Environmental Impact Assessment Report

Following the formal Pre-Application Consultation Event open to port stakeholders in October 2024, Port of Cromarty Firth submitted their Marine and Dredging License applications to Scottish Government for the Phase 5 Development on the 31st January 2025. This includes a full Environmental Impact Assessment (EIA) and a number of supporting / supplementary documents.

The submission documents are available to view below, and a hard copy is available to view at The Port Office in Invergordon.

About the Port of Cromarty Firth

Established in 1973, Port of Cromarty Firth (PoCF) is a Trust Port. It has no
shareholders and 100% of its profits are reinvested in the Port, for the benefit
of its stakeholders. Stakeholders include the local community, Port users,
employees, local and regional businesses, and local and national government.

PoCF’s mission is to act as a key economic enabler in the region (already
generating £275 million annually for the Highland economy) and supporting
high value, exciting and diverse employment opportunities in the area.

In addition, as a harbour authority, PoCF has the responsibility for safe
navigation, and safeguarding of the environment in the Cromarty Firth.

For over 50 years the Port has successfully maintained the delicate balance
between generating economic activity and safeguarding the waters over
which we are guardians.

Drivers for Phase 5

Government Net Zero Ambition

The UK and Scottish Governments have set the goal of achieving Net Zero by 2045 and 2050 respectively.

To meet Net Zero there is a heavy reliance on renewable energy, of which off shore wind is a key component.

In the last decade offshore wind turbines have steadily increased in size and moved into deeper water.

The development of floating turbines facilitates the harnessing of wind in deep waters.

Larger port facilities are required for construction, installation and operational support to offshore windfarms, hence they have become critical to achieving the Net Zero goal.

Drivers for Phase 5

Port Requirements

The Scottish Government has set targets not only for the installation of renewable technology, but also the incorporation of ‘Local Content’ in offshore wind farm projects, ensuring Scotland benefits from both the clean energy and economic development.

Appropriate port infrastructure is essential to allow this aspiration to be realised.

Drivers for Phase 5

Floating wind technology requires ports to have:

  • Deep sheltered waters for floating technology.
  • Quays for offloading components, assembling turbines onto floating bases and to allow
    pre-commissioning to be completed.
  • Large areas of laydown to facilitate the assembly and pre-commissioning stages.
  • Heavy lift and load capabilities to move and store components.
  • Preference for a roll-on, roll-off facility for ease of component delivery.
  • Good access throughout working areas.

The Proposed Port Development

Key

Phase 5 Safeguarding Port of Cromarty Firth for Future Generations
Roll-on, Roll-off

Necessary infrastructure to be located at the north of the
Queens Dock to allow components to be driven off vessels.

Queens Dock West Quay

An option to install a quay on the western edge of the Queens Dock is incorporated into the design to allow wind turbine component delivery vessels to berth and unload, without interrupting the wind turbine assembly and pre-commissioning works.

Access Widening

Small area of land reclamation to widen the access route between phases 2 and 3 past the fishmeal shed.

Fendering

Fenders will be installed along the length of the old and new berths. This will give us plenty of flexibility and allow us to berth vessels or floating turbines.

Dredging

The berth and associated navigational areas will be dredged to provide an operational berth depth of -14m Chart Datum. To ensure stability of adjacent bed materials, appropriately designed dredge slopes could be utilised to merge the dredge pocket into the surrounding seabed.

Heavy Load Pad

A 70 x 70 metre concrete heavy load pad able to take between 25-30t/m2 supported by piles will allow a large crane to be installed.

Quay West Extension

Extension to Quay West berth of up to 450m

Bollards

Mooring bollards will be installed along the quay cope beam to aid the restraint of vessels berthed at the quay. The numbers, rating and location will be appropriatelyfor the size of vessels visiting the facility.

Land Reclamation

The land reclamation will provide 11 hectares of additional laydown. Providing a maximum combined laydown area for Phases 2-5 or over 23 hectare.

Lighting

High mast lighting towers with multiple luminaires on each tower shall be installed. The lights will be controlled such that the number of active luminaries can be restricted, with the aim of minimising light pollution and energy usage while maintaining safe illumination for the tasks in progress.

Surfacing

The Phase 5 laydown area will be finished with crushed stone, and be able to bear loads of 15 tonnes per metre squared.

Visualising the Proposed Development

Phase 5 Safeguarding Port of Cromarty Firth for Future Generations
Click to open full-sized image in new tab

This Vimeo video is blocked until you accept the related cookies.

Environmental Considerations

Bird Surveys

Breeding and winter bird surveys around the Phase 5 development and shoreline up to the Invergordon boating club have been carried out. Vantage Point (VP) surveys were conducted from King Edward Drive and at the Queens Dock area within the Port boundary to understand birds’ flight patterns in the area. The survey results are informing the ornithological impact assessment.

Coastal Processes

To understand the effect the new structure will have on the shoreline, coastal process modelling is being carried out. As the shore is designated for wintering birds, it is important to ensure this habitat is not affected.

Noise Assessment

Noise monitoring has been completed to understand the baseline noise levels in Invergordon and Balblair. Noise levels associated with construction and operational plant and vessels are being utilised to predict noise levels at local receptors.

Underwater Noise

Modelling is being carried out to provide information on noise levels associated with piling and how it travels through the Firth. This will inform the assessment of impacts on marine mammals.

Tern Management Plan

This is being developed for all PoCF operations to safeguard both common and Arctic tern which utilise Invergordon Service Base for breeding activities, while ensuring worker safety. This will be a live document updated to take into account learning.

Marine Mammals

Porpoise, seals and dolphins regularly utilise the Cromarty Firth. The effects of construction noise, water quality and vessel movements are being assessed. Data collected during previous construction works in the Firth are being utilised to inform this. A marine mammal protection plan will be in place for construction works.

Archaeology and Cultural Heritage

Assessments have been undertaken to demonstrate that the potential effects on setting of features such as the Thieves Stone and Rosskeen church are non-significant. Protocols will be in place during construction in case any previous unknown artifacts are discovered.

Aviation

Discussions are planned to agree protocols for informing aviation authorities of when large structures will be in the port area.

Traffic

A traffic assessment is being conducted, however, effects are expected to be similar to those associated with the construction of Phase 4, as the majority of materials will be delivered by sea.

Landscape and Visual

Impacts on the landscape are being considered of the operational activities. Photomontages and 3D modelling is being undertaken.

Climate Change

Greenhouse gas emissions associated with the full lifecycle of Phase 5 are being considered by undertaking carbon calculations.

What Happens Next?

The Port applied to the Marine Directorate for the necessary Marine and Dredge Licences in January 2025. This is the equivalent of planning permission, but for water-based developments. The application, which was supported by the Environmental Impact Assessment (see links above), was approved in July. This followed feedback from statutory stakeholders including (please insert list as in current para) , and a public consultation.  

Work is expected to begin on construction in Spring 2026. Please see the ‘How We Will Build It’ section above for more details. We will update this page periodically to share the latest plans and progress.